There’s a reason farmers with the Dolores Project get on-demand, pressurized irrigation water delivered to the edge of their fields.
Five automated, high-tech pumping stations do the heavy lifting of pulling water from canals and pushing it through pipes to farms. Another pump system at the Great Cut Dike pulls water from McPhee Reservoir into the Dove Creek Canal and onto the pumping stations.
The Dolores Water Conservancy District and the Bureau of Reclamation have teamed up for $8 million worth of upgrades for the 20-year-old pumping stations.
The four-year plan includes upgrading the electronic communication control system, or SCADA, which operates irrigation deliveries from a main control room.
So far, three out of six pumping plants have been overhauled: Fairview, Pleasant View and Ruin Canyon. Next on the list are Dove Creek, Cahone, the Great Cut Dike and the SCADA system. Final upgrades will begin after irrigation seasons and be completed over the next two years.
Water officials and engineers touted the upgrades during a public tour Thursday at the Pleasant View pump station. At Ruin Canyon, two pumps were rebuilt, and two variable-speed electric motors were replaced. The electronic drive systems were also replaced.
The same upgrade occurred at the Ruin Canyon pump station, with a total cost for both upgrades of $1.25 million.
“They are more efficient, run cooler and require less maintenance,” said DWCD engineer Lloyd Johnson. “They will last another 20 to 25 years.”
The variable speed pumps adjust to irrigation demand. As the pressure fluctuates, the electronic drive system directs the pumps to adjust and keep the pressure steady. The drive system automatically turns on other static pumps as demand requires.
“We’re here to meet demand of the farmer,” said engineer Ken Curtis. “They pay high dollar for volume when they want it, and that is why we have a big crew of electricians and mechanics to ensure it is all working.”
The Bureau of Reclamation built the dams and reservoirs and pays to update them, said Brent Rhees, BOR’s regional director for the Upper Colorado River region.
He explained that a portion of power revenues generated from Glen Canyon dam and other BOR hydro-electric plants are set aside to pay for project upgrades like the one at the Dolores Project.
“These upgrades are satisfying to see because they keep us grounded in our mission to deliver water,” Rheese said. “The BOR has transitioned to resource management of existing projects.”
DWCD chipped in $1 million toward the project.